A pre-commencement meeting has been held for the construction of 55 kilometres Dunkwa- Twifo Praso-Assin Fosu Road.
The 18 months Cocoa Road Project is to begin in 14 days time. The contractor, Nana Kwesi Bosomefi of MAWUMS Construction Limited who held a meeting with the authorities of Twifo-Atti Morkwa District Assembly was also sent to site to determine where to start and where to end.
Scope of Works for the Rehabilitation and Upgrading of Aboabo-Asikuma-Dunkwa Road Project (Km 0.00-55.00)
The works involves the construction of a 55Km single carriageway road with two lanes to a double surface dressing finish. The duration for the project is 40 calendar months with commencement date being 9th March, 2020.
Work activities involved include;
• Earthworks
• Pavement Works (Subbase and Base)
• Surfacing Works (Primer seal, Firs seal and Second seal)
• Construction of Drainage structures (concrete U-drains of various sizes, trapezoidal drains, pipe culverts of various sizes and configurations, reinforced concrete box culverts of various sizes and configurations
• Construction of reinforced concrete retaining wall
• Construction of bus bays
• Road furniture works (traffic signs and road markings)